Foam Concrete ReferenceAn independent technical resource on foam concrete and cellular lightweight concrete

Mix design and calculation

Foam concrete mix design runs backwards from the density target. You fix the dry density, derive the solids that produce it, calculate the volume left over, and fill that volume with foam. The arithmetic is simple enough to do on site, and doing it properly is the difference between a repeatable product and a series of experiments.

The absolute volume method

Every cubic metre of foam concrete is made of solids, water and air, and the three volumes sum to one. Take one cubic metre of finished material as the basis and work in absolute volumes:

Vcement + Vfiller + Vwater + Vfoam = 1.000 m3

where each solid volume is its mass divided by its particle density: cement ≈ 3100 kg/m3, siliceous sand ≈ 2650 kg/m3, fly ash ≈ 2200 kg/m3, GGBS ≈ 2900 kg/m3, water = 1000 kg/m3.

The procedure is four steps:

  1. Fix the target oven-dry density.
  2. Choose binder and filler contents that produce that dry density.
  3. Choose a water/binder ratio and compute the mixing water.
  4. Sum the three absolute volumes and subtract from 1.000 — the remainder is the foam volume.

The foam volume, not the foam mass, is what gets dosed. Foam mass is then simply the volume multiplied by the measured foam density, and it is small: at 50 g/L, even 700 litres of foam weighs only 35 kg.

Predicting dry density from the solids

Oven-dry density is not the sum of the solids alone, because cement chemically binds part of its mixing water and retains it through oven drying. The working relationship used throughout the foam concrete literature is:

Dry density estimate

ρdry ≈ 1.2 × (cement + supplementary binder) + filler   [kg/m3]

The factor of 1.2 accounts for roughly 20 % of the binder mass being retained as chemically bound water in a fully hydrated paste. It is an estimate: mixes with high fly ash content or incomplete hydration sit slightly below it, very rich mixes slightly above. Every plant should calibrate its own factor against measured oven-dry densities within the first few production runs, after which the prediction is generally good to within 20 to 30 kg/m3.

Worked example: 1000 kg/m3 block mix

Target: 1000 kg/m3 oven-dry, sand-containing mix for load-bearing blocks.

Step 1 — solids

Choose a binder content of 400 kg/m3 CEM I. Rearranging the dry density relationship:

sand = 1000 − 1.2 × 400 = 1000 − 480 = 520 kg/m3

Step 2 — water

At w/b = 0.50: water = 0.50 × 400 = 200 kg/m3

Step 3 — absolute volumes

ComponentMassParticle densityVolume
CEM I400 kg3100 kg/m30.129 m3
Sand, 0–2 mm520 kg2650 kg/m30.196 m3
Water200 kg1000 kg/m30.200 m3
Slurry total1120 kg0.525 m3

Step 4 — foam

Foam volume = 1.000 − 0.525 = 0.475 m3 = 475 litres

At a measured foam density of 50 g/L, foam mass = 0.475 × 50 = 23.8 kg

Result

Predicted wet density = 400 + 520 + 200 + 23.8 = 1144 kg/m3, against a target oven-dry density of 1000 kg/m3. The 144 kg/m3 difference is the free water that will leave during drying. 1144 kg/m3 ± 3 % is the number the batching operator checks.

Worked example: 400 kg/m3 insulating screed

Target: 400 kg/m3 oven-dry, neat cement mix for an insulating roof screed.

Step 1 — solids

No filler at this density; the mix is cement paste and foam. Binder = 400 / 1.2 = 333 kg/m3, rounded to 335 kg/m3.

Step 2 — water

At w/b = 0.55, higher because the slurry must stay fluid without a superplasticiser: water = 0.55 × 335 = 184 kg/m3

Step 3 — absolute volumes

ComponentMassParticle densityVolume
CEM I335 kg3100 kg/m30.108 m3
Water184 kg1000 kg/m30.184 m3
Slurry total519 kg0.292 m3

Step 4 — foam

Foam volume = 1.000 − 0.292 = 0.708 m3 = 708 litres, so the material is just under 71 % air by volume.

At 50 g/L, foam mass = 0.708 × 50 = 35.4 kg

Result

Predicted wet density = 335 + 184 + 35.4 = 554 kg/m3 against a 400 kg/m3 dry target. Note how much larger the wet-to-dry gap is in proportion at low density: 154 kg/m3 here is 38 % of the dry density, against 14 % in the first example. Anyone who takes a wet density reading as if it were the dry density will reject good material at 1000 kg/m3 and accept bad material at 400.

Foaming agent consumption

Foam is generated from a diluted solution, so concentrate consumption follows from the foam volume, the foam density and the dilution ratio:

concentrate [L] = foam volume [m3] × foam density [kg/m3] ÷ (1 + dilution ratio), taking the solution density as approximately 1 kg/L.

For the 400 kg/m3 screed above, at 1:30 dilution:

foaming solution = 0.708 × 50 = 35.4 kg ≈ 35.4 L  →  concentrate = 35.4 ÷ 31 = 1.14 litres per m3

For the 1000 kg/m3 block mix: 0.475 × 50 = 23.8 L of solution, so 0.77 litres per m3.

Roughly one litre of concentrate per cubic metre is a serviceable planning figure across the common density range, falling as density rises. It makes the agent a small share of material cost and a large share of technical risk — which is the right way round to think about selecting one.

Wet density as a production control

Wet density is measured, dry density is specified, and they are not the same number. The gap is the free water: mixing water that is neither chemically bound nor retained after oven drying, plus the water carried in by the foam.

Wet-to-dry difference from the worked examples. The proportional gap grows sharply as density falls, because water content per cubic metre falls much more slowly than solids content.
Dry densityPredicted wet densityDifferenceAs % of dry
400 kg/m3554 kg/m3+15438 %
1000 kg/m31144 kg/m3+14414 %

Calculate the wet density target for each mix, write it on the batch sheet, and check it on every batch. Do not carry a wet density target across from one mix design to another.

Job quantities and waste allowance

Volume calculation is the ordinary geometry, with two foam-concrete-specific adjustments.

Worked example. An insulating roof screed, 250 m2 at 80 mm nominal thickness:

Two points that catch people out:

Then, for costing, convert to materials with the mix design: 24 m3 of the 400 kg/m3 screed above needs 24 × 335 = 8040 kg of cement — about 161 bags at 50 kg, or a part silo load — 4.4 m3 of water, 27 litres of foaming agent concentrate, and 17 m3 of generated foam.

Sizing the plant for the job

Foam demand is the number that decides whether the plant can keep up. Continuing the same job:

Commercial foam generators are rated from roughly 10 to over 100 m3/h, so the generator is almost never the bottleneck. In practice the limits are, in order: mixer batch cycle time, pump throughput on the discharge line, and — on any job with lift-height constraints — the time each lift needs to stiffen before the next can go on. Size against those, and check the generator only to confirm it is not undersized for a very low-density mix, where foam demand per cubic metre is at its highest.

Last reviewed: